Construction in Rideau-Goulbourn and Drop-In Sessions

Congratulations to Rideau-Goulbourn residents Sanchit and Riya Gupta on receiving the Mayor’s City Builder Award at Council on Wednesday, May 22. The Guptas established a chapter of MealCare, a non-profit organization that aims to combat food waste, in Ottawa. Working with local restaurants, university cafeterias and grocery stores, the Guptas take in surplus food, and, with the help of fellow volunteers, redirect it to shelters and soup kitchens where it is needed most.

Congratulations to Rideau-Goulbourn residents Sanchit and Riya Gupta on receiving the Mayor’s City Builder Award at Council on Wednesday, May 22. The Guptas established a chapter of MealCare, a non-profit organization that aims to combat food waste, in Ottawa. Working with local restaurants, university cafeterias and grocery stores, the Guptas take in surplus food, and, with the help of fellow volunteers, redirect it to shelters and soup kitchens where it is needed most.

In my most recent column, at the beginning of May, I highlighted the many culvert replacement projects that were scheduled to take place this summer. Many of these culvert renewals will lead directly into our roads program for 2020, such as Roger Stevens Drive and the other part of Rideau Valley Drive North. For now, though, I would like to focus on 2019 and let you know what you can expect to see under construction throughout Rideau-Goulbourn. Spoiler Alert: It is a lot.

We will begin with three major capital projects, two of which are ongoing. The McBean Street Bridge is still on schedule to re-open in December 2019. Construction will continue throughout the summer. The west side of the bridge is nearing completion following which the east side of the bridge will be dismantled, requiring another full closure of the bridge. We will continue to provide updates on this project. The Kanata South Link project continues as well with the widening of Old Richmond Road, between Hope Side Road and West Hunt Club as well as the construction of the roundabout at Hope Side Road. Finally, the intersection of Prince of Wales Drive and Bankfield Road will be under construction this summer as the City adds turning lanes in all directions. Additionally, Bankfield Road will be widened back to First Line Road and a signalized intersection will be installed at that point.

Onto road renewal, we have a number of Fall 2018 projects that were delayed due to the early winter that will get underway as soon as possible. Those include the McBean Street intersection with Goodstown Road, the Owlshead Road intersection with Munster Road, as well as portions of Dobson Lane, McCordick Road, and Third Line Road. These projects have already been awarded and will begin when half load restrictions are lifted from our roads. The list of 2019 road renewal projects in Rideau-Goulbourn include: 

  • Joy’s Road (Ottawa to Franktown)

  • Rideau Valley Drive North (Roger Stevens to Rideau Narrows)

  • Fallowfield Road (Eagleson to Huntley)

  • Barnsdale Road (Moodie to 416)

  • Barnsdale Road (Greenbank to Prince of Wales)

  • Hazeldean Road (Jinkinson to Carp)

  • McBean Street (Rail Crossing)

  • Dwyer Hill Road (Rail Crossing)

  • Manotick Main Street (Bankfield to Bridge)

  • Strachan (West of McBean)

  • Longfields Drive (Prince of Wales to Golflinks)

  • Carp Road (Hazeldean to Westbrook)

  • Mackey Road (Malakoff to Viola)

On our gravel roads, Paden Road will see its final lift in the two step rural road upgrade process between Harnett Road and Malakoff Road. Black’s Side Road will be upgraded using the same process this year and next between Ridingview Crescent and Flewellyn Road. McCordick Road, between Mackey Road and Cowell Road, will see new guiderails installed.

Some construction will also take place in a few of Rideau-Goulbourn’s many parks and also on a new one. Sarah McCarthy Park will see construction begin this month with a slated completion date of July. It will be Richmond’s newest park located on Cedarstone Drive. Keeping in Richmond, some final touches will be done on the work that took place in King’s Grant Park last year and the play structures at Richmond Lions Park will be replaced shortly. In Manotick, a collaborative effort between residents and my office has resulted in some new features being added to Gordon & Ivy Scharf Park. That work will also begin shortly.

Finally, in some less exciting but important nonetheless news, nearly $20M will be spent at our Trail Road waste facility which includes the replacement of the scale house and the capping of Stage 2 of the landfill. The landfill has a total of five stages. This is form part of a larger discussion in June as the Environment Committee begins discussing waste diversion and the Solid Waste Master Plan.

Drop-In Sessions

Our drop in sessions will be going on hiatus during the month of June due to the pending addition to my family but we will be back on schedule in July. I can imagine the stress this might cause you so, as always, feel free to contact my office anytime and we will do our best to assist. July will come before you know it and you can come visit at one of our next drop in sessions, with the first likely being held in Richmond.

*****

If you have any comments, questions or concerns, please feel free to email me at [email protected] or contact me by phone at 613-580-2491. For information on Rideau-Goulbourn issues, please visit RideauGoulbourn.ca.

2017 Draft Budget and Future Projects in Rideau-Goulbourn

The 2017 Draft Budget was tabled on November 9, 2016. As part of the pre-budget consultation process, Councillors conducted information sessions from mid-September to mid-October, providing information on the municipal budget process to residents and getting views and ideas on the priorities for this draft budget. With the 2017 Draft Budget tabled, there are still opportunities for residents to offer comments and input before the final Budget goes to Council for consideration on Wednesday, December 14th.  Information on the 2017 Budget is available at Ottawa.ca/budget2017 and you can submit comments via email at [email protected].

The draft budget includes a predictable 2% increase in keeping with the previous three budgets. It takes into account recent changes in the bureaucracy at City Hall that created an annual operating savings of approximately $18M. It features more money for roads, snow maintenance and parks. It also features the introduction of a low income transit pass.

In Rideau-Goulbourn, residents can expect to see a continuation of our commitment to infrastructure renewal with the resurfacing of William McEwen Drive, Shea Road and Bleeks Road. Outside of the ward, Prince of Wales Drive will also be resurfaced between Strandherd Drive and Hunt Club Road. The hard surfacing of Mackey Road will be completed this summer and pavement preservation treatment projects will take place along McCordick Road (South of Mackey Road), Third Line Road and Harnett Road. The City will also be microsurfacing Donnelly Drive between Merlyn Wilson and the City of Ottawa boundary, just west of Burritt’s Rapids. Residents on the north end of Long Island in Manotick will see the renewal of the McLean Bridge near the entrance to David Bartlett Park.

When it comes to sidewalks and cycling projects, the Federal Government has provided some funding that will go toward improving cycling in the rural area in the form of paved shoulders. These projects are not yet determined. There is also federal money that will be spent on exploring opportunities to improve cycling along Bridge Street. The primary focus will be the two bridges. With bridge reconstruction still several years away, planning now will feed into that work down the road. The 2017 Budget also identifies upgrades to the Beaverwood sidewalk, between Manotick Main Street and Ann Street. This will bring the sidewalk up to current standards.

There are several Parks & Recreation projects around the ward as well including two previously funded projects; the Manotick Arena expansion and the Remembrance Park in Dickinson Square. There is also design and construction on two parks in Richmond; King’s Grant Park and a new park on Nixon Farm Drive which will be named Sarah McCarthy Park. These two were also partially funded and announced in the 2016 Budget. In addition to the expansion at the Manotick Arena, there will also be lifecycle works completed at the same time in the form of roof replacement, septic system decommissioning, fire alarm system replacement and new flooring. Design work will also begin on replacing play structure equipment in Blue Rock Park in Kars and Richmond Lions Park.

As mentioned earlier, more information on the budget is available at www.ottawa.ca/budget2017. Please don’t hesitate to contact me should you have any questions.

Snow Go Program

Need help clearing your driveway and/or walkway during the winter? The Snow Go Program can help you. This program is divided into two parts to match your individual needs to the appropriate service. The two programs are as follows:

The Snow Go Program provides a matching service for seniors and people with disabilities looking to hire an individual or contractor to clear snow from private driveways and walkways. Residents who participate in this program are responsible for paying the individual or contractor removing the snow.

The Snow Go Assist Program provides financial assistance to eligible low-income seniors or persons with disabilities looking to hire an individual or contractor to clear snow from private driveways and walkways.  Approved participants may be reimbursed for 50% of the cost of snow clearing per event, up to a seasonal maximum of $250. Rural applicants, who pay excessively high costs for snow removal, as defined by staff, are eligible up to 50% of the cost of snow clearing for their private driveways and walkways per event, up to a maximum of $450 per term.

Check ottawa.ca/snowgo to find the agency that services your neighbourhood.

*****

If you have any comments, questions or concerns, please feel free to email me at [email protected] or contact me by phone at 613-580-2491. For information on Rideau-Goulbourn issues, please visit RideauGoulbourn.ca.